Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
6W785 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : कार्यालय जिला आपदा प्रबंधन प्राधिकरण के पत्र सं0 1094/तेरह-24 सी0आर0ए0/दै0आ0/2021-22 दिनांक 23.03.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1.29
Resanction Cost :
1.29
Tentative Cost :
1.29
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 1.29
Demand : 1.29
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
23 Mar 2023
Tentative Completion date:
8 months 2 weeks ago
31 Oct 2023
Actual Completion Date:
3 months 3 weeks ago
21 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 02-Apr-2024
Physical Peramenters