Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.74 | 1.74 | 1.740 | 0 | 0.000 | 0.000 |
6W797 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाइत संख्या 31978 दिनांक 04.05.2023
TS Amount (lakhs) : 98.88 Lacs
Financial Detail
Sanction Cost : 98.88 Lacs
Resanction Cost : 99.88 Lacs
Exp. Upto Last Fy : 36.84 Lacs
For CFY 2024-2025
Remaining : 63.04 Lacs
Demand : 25.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 36.84 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 2 weeks ago
04 May 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
1 month 2 weeks ago
29 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 30-Mar-2024