Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.8 | 5.8 | 0.000 | 5.8 | 5.800 | 2.200 |
6W798 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियंता एवं विभागाध्यक्ष के पत्रांक सं0 895/07याता0-पी0एम0जी0एस0वाई0-नि0।।। दिनांक 16.05.2023
TS Amount (lakhs) : 151.21 Lacs
Financial Detail
Sanction Cost : 151.21 Lacs
Resanction Cost : 151.21 Lacs
Exp. Upto Last Fy : 41.71 Lacs
For CFY 2024-2025
Remaining : 109.50 Lacs
Demand : 70.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 41.71 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 55 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
2 months 1 week from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.20 किमी0 पी सी का कार्य पूर्ण। -- as on 09-May-2024
Physical Peramenters