Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.8 | 5.8 | 0.000 | 5.8 | 5.800 | 5.800 |
6W798 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियंता एवं विभागाध्यक्ष के पत्रांक सं0 895/07याता0-पी0एम0जी0एस0वाई0-नि0।।। दिनांक 16.05.2023
TS Amount (lakhs) : 151.21 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
151.21
Resanction Cost :
151.21
Tentative Cost :
151.21
Exp. Upto Last Fy : 41.71
For CFY 2024-2025
Remaining : 109.50
Demand : 70.00
Allotment : 32.41
Exp in CFY : 72.53
Total Up to Date Exp : 114.24
Work completed
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
1 month 1 week ago
05 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 05-Jun-2024
Physical Peramenters