Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 3.000 | 0.000 |
6W801 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई0 फाईल सं0 50154 दिनांक 17.05.2023
TS Amount (lakhs) : 214.58 Lacs
Financial Detail
Sanction Cost : 214.58 Lacs
Resanction Cost : 214.58 Lacs
Exp. Upto Last Fy : 81.24 Lacs
For CFY 2024-2025
Remaining : 133.34 Lacs
Demand : 60.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 81.24 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
1 year 2 days ago
17 May 2023
Tentative Completion date:
6 months 1 week from now
30 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिंग, इंटर एवं टाप कोट का कार्य प्रगति पर। -- as on 12-Apr-2024
Physical Peramenters