Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 3.000 | 3.000 |
6W801 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई0 फाईल सं0 50154 दिनांक 17.05.2023
TS Amount (lakhs) : 214.58 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
214.58
Resanction Cost :
214.58
Tentative Cost :
214.58
Exp. Upto Last Fy : 81.24
For CFY 2024-2025
Remaining : 133.34
Demand : 60.00
Allotment : 84.60
Exp in CFY : 84.67
Total Up to Date Exp : 165.90
Work completed
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
17 May 2023
Tentative Completion date:
3 weeks 1 day ago
25 Jun 2024
Actual Completion Date:
3 weeks 1 day ago
25 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 02-Jul-2024
Physical Peramenters