Work Profile Report [6W806]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सुं0 973(1)/XVIII-b-1/2023-15(9)/2022 दिनांक 19.07.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
155.09
Resanction Cost :
155.09
Tentative Cost :
155.09
Exp. Upto Last Fy :
39.68
For CFY 2025-2026
Remaining :
115.41
Demand :
90.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
39.68
Work completed
Sanction on : 2 years 5 months ago
19 Jul 2023
Physical Progress:
At start of FY 2025-2026 :
60 %
Up to Date :
100 %
Tentative Completion date on : 1 week 1 day ago
31 Dec 2025
Actual Completion Date : 2 weeks 3 days ago
22 Dec 2025
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 22-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: