Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
6W809 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी बागे0 के पत्र सं0 716/जि0यो0(1)/2023-24 दिनांक 06.07.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 20.00 Lacs
Resanction Cost : 20.00 Lacs
Exp. Upto Last Fy : 7.91 Lacs
For CFY 2024-2025
Remaining : 12.09 Lacs
Demand : 12.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 7.91 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
10 months 3 hours ago
19 Jul 2023
Tentative Completion date:
7 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पैदल मार्ग का निर्माण प्रगति पर। -- as on 06-Feb-2024