Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
6W810 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी बागे0 के पत्र सं0 716/जि0यो0(1)/2023-24 दिनांक 06.07.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 30.00 Lacs
Resanction Cost : 30.00 Lacs
Exp. Upto Last Fy : 19.31 Lacs
For CFY 2024-2025
Remaining : 10.69 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 19.31 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
10 months 2 hours ago
19 Jul 2023
Tentative Completion date:
8 months 1 week from now
31 Jan 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पैदल मार्ग का निर्माण प्रगति पर। -- as on 06-Feb-2024
Physical Peramenters