Work Profile Report [6W819]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी बागे0 के पत्र सं0 716/जि0यो0(1)/2023-24 दिनांक 06.07.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
30.00
Resanction Cost :
30.00
Tentative Cost :
30.00
Exp. Upto Last Fy :
15.41
For CFY 2024-2025
Remaining :
14.59
Demand :
14.00
Allotment :
10.11
Exp in CFY :
10.11
Total Up to Date Exp :
25.52
Construction Started
Sanction on : 1 year 5 months ago
06 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
55 %
Up to Date :
55 %
Tentative Completion date on : 5 days 23 hours from now
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
टाइलिंग का कार्य प्रगति पर। -- as on 06-Feb-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand