Work Profile Report [6W832]

बाफिला गाॅव के बाफिला गधेरे में 15 मी0 पुलिया का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी बागे0 के पत्र सं0 716/जि0यो0(1)/2023-24 दिनांक 06.07.2023

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

30.00

Resanction Cost :

30.00

Tentative Cost :

30.00

Exp. Upto Last Fy :

7.08

For CFY 2024-2025

Remaining :

22.92

Demand :

22.00

Allotment :

3.10

Exp in CFY :

3.10

Total Up to Date Exp :

10.18

Construction Started

Sanction on : 1 year 5 months ago

06 Jul 2023

Physical Progress:

At start of FY 2024-2025 :

5 %

Up to Date :

5 %

Tentative Completion date on : 2 months 3 days from now

28 Feb 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Jobs
1
0
0
0
0

Remark

view all

अबटमेंट खुदान का कार्य प्रगति पर। -- as on 12-Mar-2024

Rating : 44

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand