Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 0 | 0 | 0 | 0 |
6W832 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी बागे0 के पत्र सं0 716/जि0यो0(1)/2023-24 दिनांक 06.07.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
30.00
Resanction Cost :
30.00
Tentative Cost :
30.00
Exp. Upto Last Fy : 7.08
For CFY 2024-2025
Remaining : 22.92
Demand : 22.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 7.08
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 5 %
Sanction on :
1 year 1 week ago
06 Jul 2023
Tentative Completion date:
7 months 1 week from now
28 Feb 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अबटमेंट खुदान का कार्य प्रगति पर। -- as on 12-Mar-2024
Physical Peramenters