Work Profile

6W833 :

No Pic Avilable Time series Gantt
कर्मी के अडिया तोक में लगभग 06 मी0 पुलिया


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी बागे0 के पत्र सं0 716/जि0यो0(1)/2023-24 दिनांक 06.07.2023

TS Amount (lakhs) : 0 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

8.00

Resanction Cost :

8.00

Tentative Cost :

8.00

Exp. Upto Last Fy : 0.00

For CFY 2024-2025

Remaining : 8.00

Demand : 8.00

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 0.00

Construction Started

Physical Progress:

At start of FY 2024-2025 : 15 %

Up to Date : 15 %

Sanction on :
1 year 1 week ago
06 Jul 2023


Tentative Completion date:
8 months 1 week from now
31 Mar 2025


Actual Completion Date:
Not Yet Reported


Rating : 38

Remark

Bottelneck: no issue


अबटमेंटो के खुदान का कार्य प्रगति पर। -- as on 06-Mar-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Jobs 1 1 0 1 1 0
Currently only Bank Gaurantee information is avilable