Work Profile Report [6W837]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी बागे0 के पत्र सं0 716/जि0यो0(1)/2023-24 दिनांक 06.07.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
25.00
Resanction Cost :
25.00
Tentative Cost :
25.00
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
25.00
Demand :
10.00
Allotment :
0.00
Exp in CFY :
12.59
Total Up to Date Exp :
12.59
Construction Started
Sanction on : 1 year 4 months ago
06 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
10 %
Tentative Completion date on : 6 months 1 week from now
31 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अबटमेंट खुदान का कार्य प्रगति पर। -- as on 12-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand