Work Profile Report [6W841]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : ई फाइत संख्या 51057 दिनांक 07.08.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
122.22
Resanction Cost :
122.22
Tentative Cost :
107.00
Saving
15.22
Exp. Upto Last Fy :
57.85
For CFY 2025-2026
Remaining :
64.37
Demand :
40.00
Allotment :
27.37
Exp in CFY :
25.63
Total Up to Date Exp :
83.48
Work completed
Sanction on : 2 years 4 months ago
07 Aug 2023
Physical Progress:
At start of FY 2025-2026 :
60 %
Up to Date :
100 %
Tentative Completion date on : 5 months 2 weeks ago
01 Jul 2025
Actual Completion Date : 5 months 2 weeks ago
01 Jul 2025
Physical Linear Components
Remark
Overall Saving 15.22 has been recorded as expected cost of work reduced from 122.22 to 107 . -- as on 01-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: