Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 1.000 | 3 | 3.000 | 1.000 |
6W847 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाइत संख्या 31978 दिनांक 27.09.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 237.81 Lacs
Resanction Cost : 237.81 Lacs
Exp. Upto Last Fy : 131.21 Lacs
For CFY 2024-2025
Remaining : 106.60 Lacs
Demand : 50.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 45.86 Lacs
Total Up to Date Exp : 177.07 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 80 %
Sanction on :
7 months 3 weeks ago
27 Sep 2023
Tentative Completion date:
3 months 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.00 किमी0 पार्ट-।। का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 09-May-2024