Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 1.000 | 3 | 3.000 | 3.000 |
6W847 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाइत संख्या 31978 दिनांक 27.09.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
237.81
Resanction Cost :
237.81
Tentative Cost :
237.81
Exp. Upto Last Fy : 131.21
For CFY 2024-2025
Remaining : 106.60
Demand : 50.00
Allotment : 49.95
Exp in CFY : 52.96
Total Up to Date Exp : 184.17
Work completed
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 100 %
Sanction on :
9 months 2 weeks ago
27 Sep 2023
Tentative Completion date:
1 month 1 week from now
31 Aug 2024
Actual Completion Date:
1 month 2 weeks ago
01 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 01-Jun-2024
Physical Peramenters