Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 0.000 | 10 | 4.000 | 0.000 |
6W849 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0-ई0 पत्रावली से0 48456 दिनांक 15.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 231.34 Lacs
Resanction Cost : 231.34 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 231.34 Lacs
Demand : 150.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 3 %
Up to Date : 3 %
Sanction on :
6 months 4 days ago
15 Nov 2023
Tentative Completion date:
1 year 7 months from now
31 Dec 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवारों एवं स्कपर का कार्य प्रगति पर। -- as on 29-Mar-2024
Physical Peramenters