Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 0.000 | 10 | 4.000 | 0.000 |
6W849 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0-ई0 पत्रावली से0 48456 दिनांक 15.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
231.34
Resanction Cost :
231.34
Tentative Cost :
231.34
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 231.34
Demand : 150.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 3 %
Up to Date : 25 %
Sanction on :
8 months 2 days ago
15 Nov 2023
Tentative Completion date:
1 month 3 weeks from now
11 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डिफेक्ट कटिंग का कार्य पूर्ण। दीवारों एवं स्कपर का कार्य प्रगति पर। -- as on 13-Jun-2024
Physical Peramenters