Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 0 | 0 | 0 | 0 |
6W856 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0-5082/।।।(2)/2023-01(प्रा0आ0)/2023 दिनांक 09.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
379.37
Resanction Cost :
379.37
Tentative Cost :
379.37
Exp. Upto Last Fy : 209.63
For CFY 2024-2025
Remaining : 169.74
Demand : 150.00
Allotment : 138.10
Exp in CFY : 138.10
Total Up to Date Exp : 347.74
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 50 %
Sanction on :
8 months 1 week ago
09 Nov 2023
Tentative Completion date:
2 weeks 4 days from now
05 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
क्रश बैरियर का कार्य प्रगति पर। -- as on 21-Mar-2024
Physical Peramenters