Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
6W857 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : आवास अनुभाग-2 उत्तराखण्ड शासन के ई पत्रावली सं0 33412 दिनांक 19.10.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
55.19
Resanction Cost :
55.19
Tentative Cost :
55.19
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 55.19
Demand : 40.00
Allotment : 6.11
Exp in CFY : 6.11
Total Up to Date Exp : 6.11
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 30 %
Sanction on :
8 months 4 weeks ago
19 Oct 2023
Tentative Completion date:
1 year 1 month from now
31 Aug 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार निर्माण कार्य प्रगति पर है। -- as on 13-Jun-2024
Physical Peramenters