Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
6W858 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : आवास अनुभाग-2 उत्तराखण्ड शासन के ई पत्रावली सं0 33412 दिनांक 19.10.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 46.24 Lacs
Resanction Cost : 46.24 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 46.24 Lacs
Demand : 40.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
7 months ago
19 Oct 2023
Tentative Completion date:
1 year 2 months from now
31 Jul 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार निर्माण कार्य प्रगति पर है। -- as on 02-Feb-2024
Physical Peramenters