Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
70W10 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1373/।।।(2)21-40(एम0एल0ए0) 2017 टी0सी0 4 दिनांक 21.05.2021
TS Amount (lakhs) : 61.38 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
61.38
Resanction Cost :
61.38
Tentative Cost :
61.38
Exp. Upto Last Fy : 58.03
For CFY 2024-2025
Remaining : 3.35
Demand : 3.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 58.03
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 1 month ago
21 May 2021
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
1 year 6 months ago
31 Dec 2022
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य पूर्ण। दायित्व अवशेष। अवशेष कार्य की निविदा आमंत्रित की गयी है। -- as on 04-Nov-2023
Physical Peramenters