Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
70W10 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1373/।।।(2)21-40(एम0एल0ए0) 2017 टी0सी0 4 दिनांक 21.05.2021
TS Amount (lakhs) : 61.38 Lacs
Financial Detail
Sanction Cost : 61.38 Lacs
Resanction Cost : 61.38 Lacs
Exp. Upto Last Fy : 58.03 Lacs
For CFY 2024-2025
Remaining : 3.35 Lacs
Demand : 3.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 58.03 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
21 May 2021
Tentative Completion date:
1 year 1 month ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य पूर्ण। दायित्व अवशेष। अवशेष कार्य की निविदा आमंत्रित की गयी है। -- as on 04-Nov-2023
Physical Peramenters