Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4.000 | 0 | 0.000 | 0.000 |
70W100 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1419/।।।(2)21-40(एम0एल0ए0) 2017 टी0सी0-1 दिनांक 31.05.2021
TS Amount (lakhs) : 99.88 Lacs
Financial Detail
Sanction Cost : 99.88 Lacs
Resanction Cost : 99.88 Lacs
Exp. Upto Last Fy : 90.84 Lacs
For CFY 2024-2025
Remaining : 9.04 Lacs
Demand : 9.05 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 90.84 Lacs
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
31 May 2021
Tentative Completion date:
1 year 1 month ago
31 Mar 2023
Actual Completion Date:
1 year 1 week ago
10 May 2023
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य पूर्ण। पी0सी0आर0 गठन की कार्यवाही गतिमान है। -- as on 18-Jan-2024
Physical Peramenters