Work Profile Report [70W110]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 5150/111(2)/10-18(प्रा0आ0)/2010 दिनांक 16.8.10
TS Amount (lakhs) : 18.6 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
25.20
Resanction Cost :
25.20
Tentative Cost :
25.20
Exp. Upto Last Fy :
2.26
For CFY 2024-2025
Remaining :
22.94
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.26
Construction Started
Sanction on : 14 years 4 months ago
16 Aug 2010
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
60 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रथम चरण के कार्य पूर्ण। मुआवजा गठन की कार्यवाही की जा रही है। -- as on 03-Oct-2024
Assets :
Work not linked with IM