Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 0.000 | 0.000 |
70W110 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 5150/111(2)/10-18(प्रा0आ0)/2010 दिनांक 16.8.10
TS Amount (lakhs) : 18.6 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
25.20
Resanction Cost :
25.20
Tentative Cost :
25.20
Exp. Upto Last Fy : 2.26
For CFY 2024-2025
Remaining : 22.94
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.26
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
13 years 11 months ago
16 Aug 2010
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
fद्वतीय चरण की स्वीकृfत प्राप्त ,पहाड़ कटान आfद कार्य प्रगfत पर है। मुआवजा गठन की कार्यवाही की जा रही है। -- as on 31-Mar-2021
Physical Peramenters