Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 0.000 | 0.000 |
70W127 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : fजलाfधकारी पौड़ी के पत्रांक 770fज0यो0/ लो0fन0fव0/2011-12 fद0 24.08.2011
TS Amount (lakhs) : 12.6 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
12.60
Resanction Cost :
12.60
Tentative Cost :
12.60
Exp. Upto Last Fy : 5.98
For CFY 2024-2025
Remaining : 6.62
Demand : 4.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 5.98
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
12 years 10 months ago
24 Aug 2011
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य पूर्ण। -- as on 20-Jul-2022
Physical Peramenters