Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.5 | 0.5 | 0.500 | 0 | 0.250 | 0.000 |
70W145 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : fजलाfधकारी पौड़ी के पत्रांक 1058/fज0यो0/ लो0fन0fव0/2016-17 fद0 31.08.2016
TS Amount (lakhs) : 24.81 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
24.81
Resanction Cost :
24.81
Tentative Cost :
24.81
Exp. Upto Last Fy : 17.38
For CFY 2024-2025
Remaining : 7.43
Demand : 7.43
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 17.38
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
7 years 10 months ago
31 Aug 2016
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य पूर्ण। पार्ट-2 का कार्य प्रगति पर। -- as on 28-Mar-2024
Physical Peramenters