Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 3.000 | 1 | 1.000 | 0.000 |
70W16 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1373/।।।(2)21-40(एम0एल0ए0) 2017 टी0सी0 4 दिनांक 21.05.2021
TS Amount (lakhs) : 198.18 Lacs
Financial Detail
Sanction Cost : 99.09 Lacs
Resanction Cost : 99.09 Lacs
Exp. Upto Last Fy : 55.75 Lacs
For CFY 2024-2025
Remaining : 43.34 Lacs
Demand : 43.32 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 55.75 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 90 %
Sanction on :
2 years 11 months ago
21 May 2021
Tentative Completion date:
1 week 4 days from now
31 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रारम्भिक 2.00 किमी0 में कार्य पूर्ण। अवशेष लम्बाई में ग्रामीणों द्वारा विवाद किया जा रहा था जिसे सुलझा लिया गया है। मार्ग का पुनरीक्षित संरेखण स्वीकृत। अवशेष 2.00 किमी0 लम्बाई में पहाड़ कटान का कार्य प्रगति पर। सम्पूर्ण कार्य 05/2024 तक पूर्ण कर लिया जायेगा। -- as on 06-Mar-2024
Physical Peramenters