Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 0.000 | 0.000 |
70W160 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2198(1)/111(2)/13-61(प्रा0आ0)/2012 दि0 28.03.2013
TS Amount (lakhs) : 10.59 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
18.90
Resanction Cost :
18.90
Tentative Cost :
18.90
Exp. Upto Last Fy : 11.58
For CFY 2024-2025
Remaining : 7.32
Demand : 3.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 11.58
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
11 years 3 months ago
28 Mar 2013
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य द्वितीय चरण मे स्वीकृति प्राप्त हो चुकी है। मुआवजा वितरित। -- as on 14-Jul-2022
Physical Peramenters