Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 12 | 0.000 | 12 | 0.000 | 0.000 |
70W2 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 743 /लो0नि0-1 /03-20 (प्रा0आ0) दि0 31.3.03
TS Amount (lakhs) : 51.6 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
51.60
Resanction Cost :
51.60
Tentative Cost :
51.60
Exp. Upto Last Fy : 38.17
For CFY 2024-2025
Remaining : 13.43
Demand : 3.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 38.17
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 75 %
Sanction on :
21 years 3 months ago
31 Mar 2003
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
सैद्धान्तिक स्वीकृति 8बी0/यू0सी0पी0/06/285/2009 एफ0सी0/646, दिनांक 26.08.2010 द्वारा प्राप्त। विधिवत स्वीकृति सं0 जी0आई0 2355/07.01.2010-600(3248)/2009, दि0 09.09.2010 द्वारा प्राप्त। मार्ग का निर्माण पूर्ण किया जा चुका है। नाप भूमि अधिग्रहण शेष। -- as on 26-Apr-2024
Physical Peramenters