Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.4 | 0.4 | 0.300 | 0.1 | 0.000 | 0.000 |
70W211 :
Administrative Approval Detail : fजलाfधकारी/मुख्य fवकास अfधकारी के पत्रांक 859 /वा0fज0यो0/2018-19 fद0 14.08.2018
TS Amount (lakhs) : 20 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
20.00
Resanction Cost :
20.00
Tentative Cost :
20.00
Exp. Upto Last Fy : 18.26
For CFY 2024-2025
Remaining : 1.74
Demand : 1.73
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 18.26
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 11 months ago
14 Aug 2018
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य पूर्ण।दायित्व अवशेष। -- as on 01-May-2023
Physical Peramenters