Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
70W223 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 5341/।।।(2)/18-36(एम0एल0ए0)/ 201 /टी0सी0 दि0 02.11.2018
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
39.80
Resanction Cost :
39.80
Tentative Cost :
39.80
Exp. Upto Last Fy : 12.93
For CFY 2024-2025
Remaining : 26.87
Demand : 6.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 12.93
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 35 %
Sanction on :
5 years 8 months ago
02 Nov 2018
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
स्वीकृति प्राप्त। मुआवजा गठन की कार्यवाही की जा रही है। -- as on 14-Jul-2022
Physical Peramenters