Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
70W24 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 4842(1)/।।।(2)/।।-30 (एम0एल0ए0)/2011
TS Amount (lakhs) : 33.35 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
50.40
Resanction Cost :
50.40
Tentative Cost :
50.40
Exp. Upto Last Fy : 39.21
For CFY 2024-2025
Remaining : 11.19
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 39.21
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
12 years 9 months ago
01 Oct 2011
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डी0पी0आर0 द्वितीय चरण स्टेज-1 हेतु स्वीकृत है। पहाड़ कटान का कार्य प्रगति पर। मुआवजा भुगतान अवशेष है। -- as on 08-Dec-2022
Physical Peramenters