Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
70W259 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2392/।।।(2)/21-40 (एम0एल0ए0)/ 2017 टी0सी0 -2 दिनांक 04.08.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
16.65
Resanction Cost :
16.65
Tentative Cost :
16.65
Exp. Upto Last Fy : 2.60
For CFY 2024-2025
Remaining : 14.05
Demand : 4.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.60
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
2 years 11 months ago
04 Aug 2021
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मुआवजा गठन की कार्यवाही की जानी है। द्वितीय चरण, स्टेज-। की स्वीकृति प्राप्त। -- as on 30-Jan-2024
Physical Peramenters