Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.5 | 4 | 3.500 | 0.5 | 0.500 | 0.000 |
70W273 :
Administrative Approval Detail : शा0सं0 2070/।।।(2)/21-36 (एम0एल0ए0) / 2017 टी0सी0 ।।। दिनांक 19.07.2021
TS Amount (lakhs) : 124.05 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
124.05
Resanction Cost :
124.05
Tentative Cost :
124.05
Exp. Upto Last Fy : 76.94
For CFY 2024-2025
Remaining : 47.11
Demand : 25.99
Allotment : 0.00
Exp in CFY : 0.99
Total Up to Date Exp : 77.94
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
2 years 11 months ago
19 Jul 2021
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य प्रगति पर। -- as on 19-Jul-2022
Physical Peramenters