Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
70W277 :
Administrative Approval Detail : शा0स0 4015(1)/।।।(2)/21-36 (एम0एल0ए0) /2017 टी0सी0-01 दिनांक 17.09.2021
TS Amount (lakhs) : 124.31 Lacs
Financial Detail
Sanction Cost : 124.31 Lacs
Resanction Cost : 124.31 Lacs
Exp. Upto Last Fy : 111.26 Lacs
For CFY 2024-2025
Remaining : 13.05 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 111.26 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 8 months ago
17 Sep 2021
Tentative Completion date:
1 year 1 month ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य पूर्ण। -- as on 08-Nov-2023
Physical Peramenters