Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
70W280 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1543(1)/।।।(2)/21-40 (एम0एल0ए0) /2017टी0सी0 2 दिनांक 09.06.2021
TS Amount (lakhs) : 115.95 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
115.95
Resanction Cost :
115.95
Tentative Cost :
115.95
Exp. Upto Last Fy : 107.82
For CFY 2024-2025
Remaining : 8.13
Demand : 5.49
Allotment : 0.00
Exp in CFY : 2.49
Total Up to Date Exp : 110.31
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 1 month ago
09 Jun 2021
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
1 year 6 months ago
31 Dec 2022
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य पूर्ण। -- as on 08-Nov-2023
Physical Peramenters