Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 2.500 | 0 | 0.000 | 0.000 |
70W281 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 4993(1)/।।।(2)/21-40 (एम0एल0ए0) /2017 टी0सी0 2 दिनांक 22.10.2021
TS Amount (lakhs) : 73.41 Lacs
Financial Detail
Sanction Cost : 73.41 Lacs
Resanction Cost : 73.41 Lacs
Exp. Upto Last Fy : 55.88 Lacs
For CFY 2024-2025
Remaining : 17.53 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 55.88 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 6 months ago
22 Oct 2021
Tentative Completion date:
1 year 1 month ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य पूर्ण। -- as on 04-Feb-2023
Physical Peramenters