Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 4.000 | 0.000 |
70W282 :
Administrative Approval Detail : शा0 3324/।।।(2)/21 -11 (मु0मं0घो0)/2015 दिनांक 03.09.2021
TS Amount (lakhs) : 142.06 Lacs
Financial Detail
Sanction Cost : 142.06 Lacs
Resanction Cost : 142.06 Lacs
Exp. Upto Last Fy : 58.32 Lacs
For CFY 2024-2025
Remaining : 83.74 Lacs
Demand : 50.00 Lacs
Allotment : 30.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 58.32 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 35 %
Sanction on :
2 years 8 months ago
03 Sep 2021
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पार्ट-2 का कार्य पूर्ण। एस0डी0बी0सी0 का कार्य प्रगति पर। -- as on 28-Mar-2024