Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
70W284 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 3574/(1)/।।।(2)/21-40 (एम0एल0ए0) 2017टी0सी0-1 दिनांक 10.09.2021
TS Amount (lakhs) : 203.42 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
203.42
Resanction Cost :
203.42
Tentative Cost :
203.42
Exp. Upto Last Fy : 196.20
For CFY 2024-2025
Remaining : 7.22
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 196.20
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
10 Sep 2021
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
1 year 5 months ago
16 Feb 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। पी0सी0आर0 गठित की जा रही है। -- as on 18-Jan-2024
Physical Peramenters