Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
70W295 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 3332(1)/111(2)/21-121(प्रा0आ0) /2011 दिनांक 03.09.2021
TS Amount (lakhs) : 78.83 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
78.83
Resanction Cost :
78.83
Tentative Cost :
78.83
Exp. Upto Last Fy : 58.46
For CFY 2024-2025
Remaining : 20.37
Demand : 9.32
Allotment : 0.00
Exp in CFY : 4.32
Total Up to Date Exp : 62.77
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
03 Sep 2021
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
3 months 2 weeks ago
28 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का अन्तिमीकरण किया जा रहा है। -- as on 28-Mar-2024
Physical Peramenters