Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.25 | 2.25 | 2.250 | 0 | 0.000 | 0.000 |
70W313 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शां0सं0 1638ध्।।।(2)/20-40(एम0एल0ए0)2017 टी0सी0 ।।। दिनांक 04.09.2020
TS Amount (lakhs) : 131.2 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
131.20
Resanction Cost :
131.20
Tentative Cost :
131.20
Exp. Upto Last Fy : 130.10
For CFY 2024-2025
Remaining : 1.10
Demand : 1.10
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 130.10
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 10 months ago
04 Sep 2020
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
1 year 6 months ago
31 Dec 2022
Remark
Bottelneck: no issue
कार्य पूर्ण। कार्य की पी0सी0आर0 अधीक्षण अभियन्ता पौड़ी के पत्रांक 623/783 याता0-12/2023, दि0 23.02.2024 द्वारा मुख्य अभियन्ता पौड़ी को प्रेषित। -- as on 06-Mar-2024
Physical Peramenters