Work Profile Report [70W316]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शां0सं0 1540/(1)/111(2)/20-36(एम0एल0ए0)/2017 टी0सी0 दिनांक 21.08.2020
TS Amount (lakhs) : 99.17 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
99.17
Resanction Cost :
99.17
Tentative Cost :
99.17
Exp. Upto Last Fy :
97.55
For CFY 2024-2025
Remaining :
1.62
Demand :
1.60
Allotment :
1.00
Exp in CFY :
0.00
Total Up to Date Exp :
97.55
In Maintenance After Completion
Sanction on : 4 years 4 months ago
21 Aug 2020
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 4 months ago
31 Jul 2023
Actual Completion Date : 2 years 1 week ago
15 Dec 2022
Physical Linear Components
Remark
कार्य पूर्ण। उक्त कार्य की पी0सी0आर0 दिनांक 04.12.2023 को अधी0 अभि0 पौड़ी को प्रेषित। -- as on 18-Jan-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: