Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 0.000 | 0.000 |
70W320 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 933/।।।(2)/21-36(एम0एल0ए0)/2017 दिनांक 30.03.2021
TS Amount (lakhs) : 1.31 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
34.63
Resanction Cost :
34.63
Tentative Cost :
34.63
Exp. Upto Last Fy : 0.65
For CFY 2024-2025
Remaining : 33.98
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.65
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 12 %
Up to Date : 12 %
Sanction on :
3 years 3 months ago
30 Mar 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
आपत्तियों का निराकरण कर आगणन पुनः अधीक्षण अभियन्ता पौड़ी को प्रेषित। मुआवजा गठन की कार्यवाही प्रगति पर। -- as on 28-Mar-2024
Physical Peramenters