Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
70W329 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 फाईल न0 27563 दि0 01.09.2022
TS Amount (lakhs) : 6 Lacs
Financial Detail
Sanction Cost : 6.00 Lacs
Resanction Cost : 6.00 Lacs
Exp. Upto Last Fy : 0.25 Lacs
For CFY 2024-2025
Remaining : 5.75 Lacs
Demand : 3.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.25 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
1 year 8 months ago
01 Sep 2022
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
संरेखण स्वीकृत। विस्तृत आगणन प्रेषित किया जा रहा है। -- as on 28-Mar-2024
Physical Peramenters