Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.85 | 2.85 | 0.000 | 2.85 | 0.000 | 0.000 |
70W330 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 फाईल न0 25463 दि0 30.08.2022
TS Amount (lakhs) : 93.17 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
93.17
Resanction Cost :
93.17
Tentative Cost :
93.17
Exp. Upto Last Fy : 0.52
For CFY 2024-2025
Remaining : 92.65
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.52
Technical sanction done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 15 %
Sanction on :
1 year 10 months ago
30 Aug 2022
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
वनभूमि प्रस्ताव गठन की कार्यवाही प्रगति पर। -- as on 04-Feb-2023
Physical Peramenters