Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.15 | 1.15 | 0.500 | 0.65 | 0.650 | 0.000 |
70W331 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 फाईल न0 25463 दि0 30.08.2022
TS Amount (lakhs) : 20.08 Lacs
Financial Detail
Sanction Cost : 20.08 Lacs
Resanction Cost : 20.08 Lacs
Exp. Upto Last Fy : 9.23 Lacs
For CFY 2024-2025
Remaining : 10.85 Lacs
Demand : 3.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 9.23 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
1 year 8 months ago
30 Aug 2022
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित। पहाड़ कटान का कार्य प्रगति पर। -- as on 16-Dec-2023