Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.15 | 1.15 | 0.500 | 0.65 | 0.650 | 0.000 |
70W331 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 फाईल न0 25463 दि0 30.08.2022
TS Amount (lakhs) : 20.08 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
20.08
Resanction Cost :
20.08
Tentative Cost :
20.08
Exp. Upto Last Fy : 9.23
For CFY 2024-2025
Remaining : 10.85
Demand : 3.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 9.23
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
1 year 10 months ago
30 Aug 2022
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित। पहाड़ कटान का कार्य प्रगति पर। -- as on 16-Dec-2023
Physical Peramenters