Work Profile Report [70W335]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई0 फाईल न0 36089 दि0 11.10.2022
TS Amount (lakhs) : 2.88 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2.88
Resanction Cost :
2.88
Tentative Cost :
2.88
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
2.78
Demand :
2.78
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Alignment Approved
Sanction on : 2 years 2 months ago
11 Oct 2022
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
40 %
Tentative Completion date on : 6 months 3 weeks ago
31 May 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
स्थल चयन का कार्य पूर्ण। डी0पी0आर0 गठन की कार्यवाही प्रगति पर। -- as on 01-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand