Work Profile Report [70W347]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई0 फाईल न0 27563 दि0 14.12.2022
TS Amount (lakhs) : 137.02 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
137.02
Resanction Cost :
137.02
Tentative Cost :
137.02
Exp. Upto Last Fy :
121.91
For CFY 2024-2025
Remaining :
15.11
Demand :
6.00
Allotment :
6.00
Exp in CFY :
0.62
Total Up to Date Exp :
122.53
In Maintenance After Completion
Sanction on : 1 year 11 months ago
14 Dec 2022
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 10 months 3 weeks ago
28 Dec 2023
Actual Completion Date : 1 year 1 month ago
20 Oct 2023
Physical Linear Components
Remark
कार्य पूर्ण। पी0सी0आर0 गठित की जा रही है। -- as on 18-Jan-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: