Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2.000 | 0 | 0.000 | 0.000 |
70W347 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 फाईल न0 27563 दि0 14.12.2022
TS Amount (lakhs) : 137.02 Lacs
Financial Detail
Sanction Cost : 137.02 Lacs
Resanction Cost : 137.02 Lacs
Exp. Upto Last Fy : 121.91 Lacs
For CFY 2024-2025
Remaining : 15.11 Lacs
Demand : 11.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 121.91 Lacs
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 5 months ago
14 Dec 2022
Tentative Completion date:
4 months 3 weeks ago
28 Dec 2023
Actual Completion Date:
5 months 1 week ago
08 Dec 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। पी0सी0आर0 गठित की जा रही है। -- as on 18-Jan-2024
Physical Peramenters