Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2.000 | 0 | 0.000 | 0.000 |
70W348 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 फाईल न0 27563 दि0 14.12.2022
TS Amount (lakhs) : 59.29 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
59.29
Resanction Cost :
59.29
Tentative Cost :
59.29
Exp. Upto Last Fy : 35.52
For CFY 2024-2025
Remaining : 23.77
Demand : 17.51
Allotment : 0.00
Exp in CFY : 4.98
Total Up to Date Exp : 40.50
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 7 months ago
14 Dec 2022
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
6 months 2 weeks ago
01 Jan 2024
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य पूर्ण। दायित्वों का भुगतान किया जा रहा है। -- as on 01-Jan-2024
Physical Peramenters