Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 1.000 | 1.000 |
70W401 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 फाईल न0 25463 दि0 31-03-2023
TS Amount (lakhs) : 74.68 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
74.68
Resanction Cost :
74.68
Tentative Cost :
74.68
Exp. Upto Last Fy : 13.91
For CFY 2024-2025
Remaining : 60.77
Demand : 52.58
Allotment : 50.00
Exp in CFY : 2.58
Total Up to Date Exp : 16.49
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 95 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
1 week 3 days from now
28 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 का कार्य पूर्ण। पटरी एवं नाली निर्माण का कार्य प्रगति पर। -- as on 25-Jun-2024