Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 1.000 | 0.000 |
70W401 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 फाईल न0 25463 दि0 31-03-2023
TS Amount (lakhs) : 74.68 Lacs
Financial Detail
Sanction Cost : 74.68 Lacs
Resanction Cost : 74.68 Lacs
Exp. Upto Last Fy : 13.91 Lacs
For CFY 2024-2025
Remaining : 60.77 Lacs
Demand : 50.00 Lacs
Allotment : 30.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 13.91 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
1 year 1 month ago
31 Mar 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डिफेक्ट कटिंग, स्कपर एवं सोलिंग का कार्य पूर्ण। इण्टर कोट का कार्य प्रगति पर। -- as on 28-Mar-2024