Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 3.000 | 0.000 |
70W404 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-फाइल संख्या-38666 , दिनांक-31-03-2023
TS Amount (lakhs) : 198.94 Lacs
Financial Detail
Sanction Cost : 198.94 Lacs
Resanction Cost : 198.94 Lacs
Exp. Upto Last Fy : 169.34 Lacs
For CFY 2024-2025
Remaining : 29.60 Lacs
Demand : 24.84 Lacs
Allotment : 14.99 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 169.34 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 80 %
Sanction on :
1 year 1 month ago
31 Mar 2023
Tentative Completion date:
6 months 1 week from now
30 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 का कार्य प्रगति पर। -- as on 08-May-2024
Physical Peramenters