Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
70W415 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी पौड़ी के पत्रांक 698/30 खनन/न्यास/2023-24, दि0 02.05.2023।
TS Amount (lakhs) : 116.67 Lacs
Financial Detail
Sanction Cost : 116.67 Lacs
Resanction Cost : 116.67 Lacs
Exp. Upto Last Fy : 31.70 Lacs
For CFY 2024-2025
Remaining : 84.97 Lacs
Demand : 46.67 Lacs
Allotment : 38.30 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 31.70 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
1 year 2 weeks ago
02 May 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 30-Jan-2024