Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 18 | 18 | 7.000 | 11 | 11.000 | 11.000 |
70W419 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एंव विभागाध्यक्ष, लो0नि0वि0, उत्तराखण्ड के पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई0-नि0।।।, दिनांक 16.05.2023।
TS Amount (lakhs) : 419.21 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
419.21
Resanction Cost :
419.21
Tentative Cost :
419.21
Exp. Upto Last Fy : 267.76
For CFY 2024-2025
Remaining : 151.45
Demand : 151.45
Allotment : 80.00
Exp in CFY : 89.12
Total Up to Date Exp : 356.88
Work completed
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
1 month 2 weeks ago
30 May 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का अन्तिमीकरण किया जा रहा है। -- as on 08-May-2024