Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.7 | 7.7 | 0.000 | 7.7 | 7.700 | 7.700 |
70W453 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली संख्या-48456, दिनांक 10.08.2023
TS Amount (lakhs) : 104.13 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
104.13
Resanction Cost :
104.13
Tentative Cost :
104.13
Exp. Upto Last Fy : 37.85
For CFY 2024-2025
Remaining : 66.28
Demand : 66.28
Allotment : 30.00
Exp in CFY : 0.97
Total Up to Date Exp : 38.82
Work completed
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 100 %
Sanction on :
11 months 1 week ago
10 Aug 2023
Tentative Completion date:
1 month 1 week ago
05 Jun 2024
Actual Completion Date:
1 month 2 days ago
15 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का अन्तिमीकरण किया जा रहा है। -- as on 25-Jun-2024