Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.7 | 7.7 | 0.000 | 7.7 | 7.700 | 0.000 |
70W453 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली संख्या-48456, दिनांक 10.08.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 104.13 Lacs
Resanction Cost : 104.13 Lacs
Exp. Upto Last Fy : 37.85 Lacs
For CFY 2024-2025
Remaining : 66.28 Lacs
Demand : 66.28 Lacs
Allotment : 30.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 37.85 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 50 %
Sanction on :
9 months 1 week ago
10 Aug 2023
Tentative Completion date:
2 weeks 2 days from now
05 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 का कार्य प्रगति पर। -- as on 08-May-2024
Physical Peramenters